Track your tasks
| # | Task Name | Description | Time Allotted | Proposed Date | Start Date | End Date | Time Taken | Comment | Status |
|---|---|---|---|---|---|---|---|---|---|
| 1 | updating latest changes to server - new logo, new sections | updating latest changes to server - new logo, new sections | 0 hr 30 min | 17-04-2026 10:32:51 | 17-04-2026 10:33:40 | 17-04-2026 11:32:13 | 0 hr 59 min | Completed | |
| 2 | updating latest image changes | updating latest image changes | 0 hr 20 min | 13-04-2026 15:29:38 | 13-04-2026 15:29:56 | 13-04-2026 16:34:04 | 1 hr 4 min | Completed | |
| 3 | setting github for mbpl | setting github | 0 hr 20 min | 11-04-2026 08:52:06 | 11-04-2026 08:53:21 | 11-04-2026 10:21:32 | 1 hr 28 min | Completed | |
| 4 | setting up images in site | setting up images in site | 1 hr 0 min | 11-04-2026 08:32:46 | 11-04-2026 08:33:00 | 11-04-2026 08:51:16 | 0 hr 18 min | Completed | |
| 5 | updating latest changes to server - blog, responsive changes | updating latest changes to server - blog, responsive changes | 0 hr 30 min | 10-04-2026 12:39:47 | 10-04-2026 12:47:09 | 10-04-2026 16:24:49 | 1 hr 24 min | Completed | |
| 6 | setting up in our server for demo | setting up in our server for demo | 1 hr 0 min | 10-04-2026 08:22:54 | 10-04-2026 08:23:26 | 10-04-2026 10:07:31 | 1 hr 44 min | Completed | |
| 7 | project scope break down | project scope break down | 0 hr 20 min | 02-04-2026 10:28:45 | 02-04-2026 10:29:05 | 02-04-2026 11:26:43 | 0 hr 40 min | Completed | |
| 8 | checking email issue | checking email issue | 0 hr 20 min | 31-03-2026 17:05:44 | 31-03-2026 17:06:08 | 31-03-2026 18:27:12 | 1 hr 12 min | Completed | |
| 9 | checking email issue | checking email issue | 1 hr 0 min | 30-03-2026 11:56:28 | 30-03-2026 11:56:48 | 30-03-2026 13:10:21 | 1 hr 14 min | Completed | |
| 10 | checking email deliverability issue | checking email deliverability issue | 0 hr 30 min | 27-03-2026 17:08:41 | 27-03-2026 17:09:12 | 30-03-2026 08:34:09 | 0 hr 23 min | Completed |